Management Discussion and Analysis 1. Significant events in the third Quarter of 2019 1.1 The progress in construction projects 1.1.1 Project completion - SBPL Project, a project of San Buenaventura Power Ltd
Page 2 Management Discussion and Analysis 1. Significant events in the second Quarter of 2018 The progress in construction projects - Xayaburi Project, a project of the Xayaburi Power Company Limited
Page 2 Management Discussion and Analysis 1. Significant events in the third Quarter of 2018 The progress in construction projects - Xayaburi Project, a project of the Xayaburi Power Company Limited
events in the first Quarter of 2019 1.1 The progress in construction projects - Xayaburi Project, a project of the Xayaburi Power Company Limited, (EGCO holds a 12.50% ownership interest.), is a hydro
to the commencement of commercial operation of Mount Emerald Wind Farm Project and Collinsville Solar Power Project on December 12, 2018 and March 21, 2019, respectively. In addition, cost of sales
Operation Date EBITDA Earnings before Interest, Tax, Depreciation and Amortization FX Foreign Exchange Rate IPP Independent Power Producer PPA Power Purchase Agreement SPP Small Power Producer Projects
Seven Utilities and Power Public Co.,Ltd. 73 Mahachol Building, Soi Sukhumvit 62, Sukhumvit Rd., Phrakhanong Tai, Phrakhanong BKK.10260 บมจ. เซเว่น ยูทลิิตีส์้ แอนด์ พาวเวอร์ 73 อาคารมหาชล ซอยสขุมุ
tower, design and distribute steel structure according to the drawing, power distribution and heat energy business, construction and tunneling contractor and distribution of industrial products. In the
renewable energy power plants projects of private sector The revenue from sales business was increased of MTHB 37.14 comparing to the revenue form sales business of amount MTHB 63.72 at the same period of
last year that had the amount of Baht 1.92 million, this caused from the realization of gain from investment in Green Earth Power (Thailand) Company Limited (GEP) that is the investor of solar power