2020 The Company recognizes revenue from the production line installation project and the production line test for the whole system installation, which is expected to be installed in May 2020, resulting
installation of the production line and the testing of the production line in respect of the installation of the entire production line, which was installed successfully. In July 2020, the results of the
(ThaiCERT). Given the more sophisticated cyber risks, financial institutions as service providers, and customers as users, are increasingly vulnerable to losses. In terms of cyber security readiness, however
project value of Baht 125.00 million. Under the contract, the project was due to complete in February 2018. Nevertheless, during installation, the installation areas were continuously affected by floods
steam boiler and balance of plants including manufacturing and installation 3. Registered Capital: 25,000 EUR or equal to 901,052.50 Baht (Average selling rate on 4th April 2019: 36.0421 Baht per Euro
27.63 million and THB 2.23 million respectively or equivalent to 297.10% and 314.08% respectively due to installation solar cell project 1 MW and warehouse tenants increased. Gross Profit / Margin The
million Baht compared to 38.67 million Baht and 38.41 million Baht respectively in the quarter 2/2016 due to the major reasons as follows; 1. Incomes from the production and installation of the pipeline
install due to heavy rain and flooding. Make delivery and installation delayed. In the fourth quarter of 2017, the Company has installed and delivered to the customers for installation and remaining 11
considering the capacity, readiness, and size of businesses. It also discussed the potential use of a phased approach to adjust the scope of regulations according to the specific context of in each country
follows due process of law, including collaboration with relevant agencies. In the case of STARK, upon learning of the news, we communicated with DSI our readiness to extend further collaboration, by